The recent groundbreaking of the Hudson Yards project will usher in five years of construction that will extend the High Line to West 34th Street, build platforms over the rail yards, construct massive commercial and residential high-rise towers and provide public spaces and a K-8 school for new residents.
May 2010: Oxford Properties Group partners with Related, signs contract with MTA for development right of 13 million square feet at Hudson Yards
Jan. 14, 2013: Break ground on Manhattan West — building platform
August 2013: Superstructure of South Tower completed
2014: Platform over rail yards to be completed
2014: Groundbreaking on Tower D, 80/20 housing
2014: Construction on Hudson Yards North Tower to begin
2014: High Line Section 2 to 34th Street, including interim walkway
2015: Hudson Yards South Tower completed
2016: Manhattan West open to tenants
2016: Tower D completed, with 80/20 affordable housing
2017: Culture Shed public area to be completed
2016: Entire Eastern Rail Yards completed
2017: Western Yards construction begins
2024: Entire Hudson Yards project completed